Equipment problems led Wasatch Constructors to cancel, at the last minute, a full freeway closure scheduled for Tuesday night.

The I-15 reconstruction contractor had planned to move a piece of paving machinery from the south end of the project corridor to the north end.Wasatch will try it again Wednesday night. It will close northbound I-15 for the entire 17-mile length of the project - from 10600 South to 1000 North - from 10 p.m. Wednes-day until 6 a.m. Thursday. The paving machine travels slowly, a spokesman for the contractor said.

Again, the daily I-15 work schedule is subject to change. For the latest updates, call 1-888-INFO-I15, or check the contractor's Web site at (www.I-15.com).