Full Interstate Closures

Aug. 4-6, 10 p.m.-6 a.m., northbound I-15 from 600 South to 1000 North.

Aug. 5-6, 10 p.m.-6 a.m., southbound I-15 between 1000 North and 500 South.

Ramp Closures

Aug. 5, 10 p.m.-6 a.m., southbound I-15 connection to westbound U-201.

Aug. 5-spring 2001, 24 hours, southbound I-15 ramp to westbound I-80.

Other Street Closures

Aug. 2-Sept. 15, 24 hours, 10600 South from State Street to 700 East.

Aug. 3-4, midnight-6 a.m., 4800 South beneath I-15.

Aug. 5, 10 p.m.-6 a.m., westbound U-201 from 300 West to 900 West.

Aug. 6, 9 p.m.-6 a.m., eastbound U-201 between Redwood Road and 300 West.

Upcoming Closures

Aug. 24-November, 24 hours, northbound I-15 offramp and onramp at 10600 South.

Statewide Road Closures

Aug. 2-TBA, 5600 South in Roy, between 2425 West and 3300 West.

Aug. 2-TBA, in Cedar City, bridge replacement at 200 North/200 East has closed Piute Drive and Highland Drive. Local access maintained.