SAO PAULO — Part of the stadium that will host the 2014 World Cup opener in Brazil collapsed on Wednesday, killing two workers and raising urgent new concerns whether the country will be ready for soccer's signature event.

Brazil has been plagued by a series of setbacks including cost overruns, stadium delays, accidents, labor strife and massive street protests in the run-up to the June tournament, once envisioned as a coming out party for South America's largest nation, which is also scheduled to host the Olympics in 2016.

Wednesday's accident at Sao Paulo's Itaquerao stadium occurred when a construction crane crashed into a 500-ton metal structure that in turn cut through the outer walls of the venue, destroying rows of seats and slamming into a massive LED panel that runs across the stadium's facade.

The accident could delay delivery of the stadium, which was practically finished before Wednesday's collapse. FIFA has set a December deadline for all 12 World Cup venues to be ready. The World Cup begins on June 12 with Brazil playing at the Sao Paulo stadium.

Officials said there were no major structural damages to the stadium but declined to say how much the accident may affect the delivery.

"I don't want to know about FIFA right now, we are worried about the families of the victims," former Corinthians president Andres Sanchez told a news conference.

Sanchez said two people were confirmed dead and nobody else was injured. A fire department official had said earlier that three people had died.

One of the workers, 42-year-old Fabio Luis Pereira, was inside a truck that was hit by the metal structure. The other, 44-year-old Ronaldo Oliveira dos Santos, was resting in an area which was supposed to be isolated.

"Unfortunately nobody saw him and he himself knew that he was not supposed to be there," Sanchez said. "He was napping and unfortunately there wasn't time for him to get out."

The accident happened at lunchtime, so not many of the nearly 1,700 employees working on the venue were on site when the crane collapsed on top of the metal structure, causing the deadly domino effect.

"The sound was as loud as a thunderclap or a huge explosion," said Rodrigo Vessoni, a reporter with sports daily Lance who said he had just walked out of the stadium after interviewing Sanchez. "There was a lot of running around, a lot of shouting. It was frightening. Chills ran through my entire body. It was unbelievable. The noise was metal grating on metal. It was a terrible thing to see."

An official with constructor Odebrecht said a similar metal structure had already been installed with the same crane at the other side of the venue earlier this year.

"Everything was being done according to procedure," said Frederico Barbosa, the construction site's manager. "We will have to wait for the investigation to find out what caused the crane to collapse."

Sanchez reiterated that it appeared to engineers on site that the structure of the stadium had not been compromised, meaning there could be enough time to get everything fixed in time for the World Cup. He said that around 30 percent of the stadium will be closed off pending authorities' investigations.

"Structurally very little was affected," he said.

Brazil is running against time to deliver the last six World Cup stadiums by the end of the year, although work at the Itaquerao was advanced compared to the other venues. FIFA has been pressuring local organizers to make sure all venues are ready by the December deadline so all test events can take place in time for the World Cup.

FIFA said it would not accept the same delays that plagued stadium construction before the Confederations Cup, when only two venues were delivered in time.