Transmission line gets judge's OK

Published: Saturday, July 4, 2009 12:00 a.m. MDT
PRINT | FONT + - 

BRIGHAM CITY — A judge has signed an order that will let Rocky Mountain Power continue construction of a transmission line through the city of Willard, which last week denied the company a conditional-use permit for the project.

First District Court Judge Ben Hadfield signed the order on Thursday. Rocky Mountain Power says the order lets the utility construct access roads, build base pads for power poles and perform survey work. The order will remain in effect until late July.

Rocky Mountain Power filed a lawsuit last week after the Willard City Council, on a 3-2 vote, denied the permit after taking comment and hearing from an electrical magnetic field expert.

About this ad

View Comments

DeseretNews.com encourages a civil dialogue among its readers. We welcome your thoughtful comments.

– About Comments

rss icon

Recommended in Utah

Story

Officials confirmed Friday that a man and a woman from Wyoming were killed in a plane crash.

Story

A state senator vows that proposed changes to Utah's open records law this year won't be controversial.

Story

Dozens of Cache Valley residents gathered to release balloons in memory of Charlie and Braden Powell.

In News Across Site

No. Utah sees a major earthquake every 350 years. Last one? 350 years ago.