New I-80 bridges are all in place
UDOT crews finish project a week ahead of schedule
UDOT workers help in moving the bridge into place Wednesday. Each bridge weighs between 2 million and 3 million pounds.
Jeffrey D. Allred, Deseret News
As drivers pass over I-80 on 1300 East they may notice that the once-full bridge farm is now empty. A week ahead of schedule, crews working along the interstate were able to move and lower into place seven multimillion-pound structures between Highland Drive and 300 East.
Crew members on-site Wednesday were relieved to see the project nearing completion, but their work on the interstate is far from complete, said John Montoya, site project manager. Workers have begun laying pavement along the five lanes added to the interstate and will soon be constructing noise walls.
"We're not home free yet we're not even to the midpoint yet, which is the traffic shift onto the new road," Montoya said. "This was the biggest challenge that we've completed, but there is a lot left to build."
After the lane shift, which is expected in late fall, crews will begin replacing bridges along the eastbound section of the interstate, using conventional bridge-building techniques.
In the past, the Utah Department of Transportation has used rapid bridge-building techniques at 4500 South, but crews there drove the structure in from the side and lifted it into place. For this newly completed project, crews launched the bridges from the interstate and lowered them into place. It was a first in the nation and a learning experience, Montoya said.
Montoya estimated that it took crews five to seven days to move the Highland Drive structure from the bridge farm to its final location above the street. For the first move Montoya said crews intentionally took their time to get a grasp of the many aspects involved in transporting the structures. By the time UDOT moved the 300 East bridge, it took just 36 hours from the initial move to the placement.
"When you move seven bridges you have an opportunity to learn from each one and apply those lessons to each proceeding placement," Montoya said.
Wayne Bowden, project manager for Ralph Wadsworth Construction, said that the rapid bridge project was a test to see if this kind of building technique could be done. He believes the crews passed with flying colors. Bowden said he expects to see other projects like this in the state and nation.
"I'd just like to acknowledge how hard everyone has worked to get us to this point," Montoya said. "We've had 50 to 60 guys working their guts out every day."
The days were long and hot, crew members said Wednesday. Dennis Theis, a superintendent with Mammot, a Dutch company that provided equipment for the move, said that on average he logged about 95 hours a week, but he added, "The overtime is good for the mortgage."
- KSL-TV welcomes 2 new anchors, new format
- Utah woman adopted as baby faces deportation...
- If you want to live a long time, stay in school
- Dangerous silence: Why you need to talk to...
- Tattoo change from 'Dea' to 'Death' could...
- Final movement: Retiring violinist reflects...
- Clinton man arrested in shooting death of...
- Weekend rescuers save horse in basement,...
- Dangerous silence: Why you need to talk...
28 - Studies try to find why poorer people...
27 - Sarah Palin catches flak over her Orrin...
24 - Liljenquist pushing to make name for...
21 - KSL-TV welcomes 2 new anchors, new format
17 - Utah woman adopted as baby faces...
16 - Several Utah high schools moving to...
13 - Vets heart Mitt: Romney enjoys big...
8






DeseretNews.com encourages a civil dialogue among its readers. We welcome your thoughtful comments.
— About comments