Three million pounds in motion along Utah's I-80

Published: Monday, June 23 2008 12:23 a.m. MDT

Hundreds watch Saturday as a bridge is slowly moved from 1300 East to Highland Drive. The project was delayed because of concerns about a beam.

Geoffrey McAllister, Deseret News

A man moved a 3 million-pound bridge from 1300 East to Highland Drive along I-80 Saturday night using a joy stick wired to a self-propelled modular transport system. Yet for the bridge to reach its final destination this week, it will take dish soap, wooden blocks imported from Africa and clever minds, along with lots of patience from motorists.

Moving the first bridge to be installed along I-80 begins a process of leap-frog construction that will take place between 1300 East and State Street. For months, crews have been casting the decks for seven bridges that will replace existing structures at Highland Drive, 900 East, 700 East, 600 East, 500 East and 300 East. The movement and placement of the bridges will run through the first week of August, Utah Department of Transportation officials estimate.

Crews were expecting to have the first bridge in place over the weekend, but because of concerns about a bend in the carrying beam, the project was delayed. On Sunday afternoon, crews were welding additional supports to the beam. Today, UDOT is hoping to place the bridge across the gap and begin lowering it into place.

"We're playing it safe and handling things with care," said John Montoya, project manager for the site. "It's not worth the chance. There isn't a second one."

That means commuters will face delays this morning. During bridge movements and placements, westbound I-80 will be reduced to a single lane and eastbound traffic to two. As crews are preparing for other moves, both eastbound and westbound lanes will have two lanes open.

Montoya is expecting the bridge to be resting in its final location Tuesday. Soon after the bridge is placed, crews will begin buttressing the underside of the structure so it can support other bridges as they move over Highland Drive.

To move the structures from the bridge "farm" located along the 1300 East westbound onramp, crews are using accelerated bridge construction methods that are a first for the industry. Previous bridge replacements in the state have used similar steps in the process, but the scale of the project and new approach to placing bridges is gaining attention around the nation.

UDOT officials say that the benefits from these new technologies have reduced the overall congestion of traffic through the construction process and saved both time and money for the department.

To move structures that weigh between 2 million and 3 million pounds to their designated place along I-80, crews use a self-propelled modular transport system, Montoya said. It crawls under the bridge and uses a hydraulic lift system to raise the bridge about 10 feet off the ground so it can be moved to its destination.

Get The Deseret News Everywhere

Subscribe

Mobile

RSS