Rail finally to get real

OK looms for on-ground work on commuter line

Published: Monday, April 18, 2005 12:28 a.m. MDT
 |  E-MAIL | PRINT | FONT + - 
Perhaps as early as next week, Steve Meyer plans to slip into his office and do a dance of joy.

After years of planning and preparing paperwork, Meyer expects to have approval to begin some on-the-ground work for commuter rail — a 44-mile transit project from Salt Lake City into Davis and Weber counties.

It's a milestone for the Utah Transit Authority and Meyer, manager of commuter rail construction. "Now we get to start doing something," said UTA spokesman Justin Jones.

Today, a 30-day comment period on the final environmental study of commuter rail will end. As early as the end of next week, UTA could receive one of two federal approvals that come with the completion of environmental work: the Record of Decision.

The second approval, known as a Letter of No Prejudice, should be obtained before the end of the month.

These approvals mark the midpoint of a lengthy process to complete commuter rail by early 2008. With the Letter and Record of Decision, UTA can begin negotiations to purchase property from cities and private land owners.

Story continues below
Utility work along the rail corridor could begin in June. This ranges from extension of drainage systems and relocation of gas and refinery pipes to installation of fiber optic lines.

Fill work can begin, and UTA can start negotiations to purchase new commuter rail cars. Price negotiations with the project's contractor will also begin.

"It allows us to get going," said Meyer. "The holy grail is the full-funding grant agreement, but in advance of that, it allows us to get started. These items are on the critical path and they need to get started before the full-funding agreement."

The full-funding agreement is a final federal approval that allows UTA to begin all aspects of construction. It is a "contract" between UTA and the Federal Transit Administration that determines the amount of federal funds contributed to the project, said Meyer.

The agreement could be obtained as early as this fall, according to Meyer.

Davis County leaders say sooner is better.

"A lot of people see us pushing for the Legacy Highway because that's become such a visible fight," said Wilf Sommerkorn, Davis County director of community and economic development. "We're just as aggressive with commuter rail."

The line will give residents who travel into Salt Lake County an alternative to driving, said Sommerkorn. It could also spur job growth. At least one large-scale development is being planned along the line, centered around the Farmington commuter rail station.

Comments

You can be the first to comment on this story.

Image
Deseret Morning News graphic

previousnext

Latest comments

Guess if Meyer says he's staying at Florida then he definitely is headed to...

Bronco, Kyle rubber match

ummm utah...dominating Defense???...when?...which game this year has utah...

Is there a liberal that doesn't want Palin to run? :-) BTW, I read. I know...

I totally agree with the author.

I wish I was there what a great win!

RSL championship rally Tuesday

I bet these soccer haters never commented on badminton articles, 'cause they...

This game started out as a ho hum affair then got interesting in the 3rd and...

Letters: Gays' parades offensive

12:31 p.m. I wasn't refering to Earl's comment specifically. This isn't...

Crimes up against gays, religious

Wow, so you pick and choose what data you believe, then discount facts along...

'Savior of the World' in Spanish

This could be a sting.

Advertisements