Orem roadwork ahead of schedule

But 1600 North project irritates some residents

Published: Sunday, May 14, 2006 10:44 p.m. MDT
 |  E-MAIL | PRINT | FONT + - 
OREM — Orange barrels, unpaved road and dust aren't the only things bothering Orem residents living with a construction zone on 1600 North.

Fortunately, their frustration may not last as long as they thought it would.

The $5 million construction project — to install new underground utilities and completely reconstruct the street — is 45 days ahead of schedule, city project manager Morris Flygare said.

Karma Huish lives on 1600 North and said the work sometimes has forced her to take a different route to her house, but it doesn't bother her.

"(The road) is bumpy, but you expect it to be," Huish said. "But they've always kept access for us which is good because we have to get in and out."

Huish's house is located on the edge of a cul-de-sac and the city took the corner of their lot to make the turn more manageable.

"It's progress," she said. "You have to put up with something to have it fixed."

Mark Yount isn't as quick to forgive the inflicted pains.

His home is in the heart of the construction, and he said he's dealt with with a lot of negative effects during this first phase of construction.

Story continues below
Worst is the money he said he's lost because customers of his computer and printer repair company, Wasatch Computers, have had trouble finding his house.

It's not just his business he's worried about. Yount can't get into his driveway because there's a trench blocking it.

Instead, he has to park his Honda around the corner. He also said he's been pulled over for driving down 1600 North on the way to his house.

Workers also tore up two sections of sod in Yount's yard to make room for a fire hydrant and a telephone pole, sections Yount said he hopes the city will replace.

"It's been a nightmare," Yount said. "It's not an inconvenience, it's a nightmare."

The project was scheduled to run from April 3 to June 5, with crews working on the section of the street from 600 West to 1030 West.

Flygare said construction will continue at a rapid pace if wet and stormy weather doesn't roll into the Wasatch Front.


E-mail: jelder@desnews.com

Comments

You can be the first to comment on this story.

Image

A section of Orem's 1600 North is undergoing complete reconstruction.

previousnext

Latest comments

RSL's Rimando makes 3

So Great!!! So Proud - Love RSL - Bring Home The CUP!!!!!

mr cannon's bold assertation that the purpose of the first ammendemnt as...

RSL heads to MLS title game

Great great great game!!!! Nicky Rimando is a god! We're the most complete...

I had the game on DVR and just watched it. That was the most exciting game...

RSL heads to MLS title game

financially cannot this year, but I will watch loyally, how great to hear...

This is hardly surprising. Bennett has a remarkable arrogance which is also...

RSL heads to MLS title game

I guess that is why "they play the game" as Herman Edwards would say.. ...

BYU happy to escape with victory

What was the score of the LSU vs LA tech game? Alot closer than you'd like to...

Has Fedor not said that THIS IS OUR YEAR all year long? Go back and...

This is just a small glimpse of the future with Obamacare: corruption, waste...

Advertisements
Advertisement