Pricey permits: BYU study finds big disparity among Wasatch Front cities

Published: Thursday, Feb. 23, 2006 11:31 p.m. MST
 |  E-MAIL | PRINT | FONT + - 
Thinking of developing an office building? You may want to steer clear of South Jordan, which charges developers more than $438,000 to obtain a single office building permit, according to a study released Thursday.

You may also want to avoid Herriman, where it takes more than two years to secure the permit.

In some cities, developers face an extremely long and costly battle to build new office and industrial buildings, according to Michael Roderick, president of the Utah chapter of the National Association of Industrial and Office Properties.

"If we cannot develop and deliver projects in a timely manner and a competitive manner, we are going to lose out to all these industries," Roderick said. "Salt Lake County municipalities are competing with the Denvers of the world, the Phoenixes of the world and Las Vegas for business and industry."

The $10,000 study, which was conducted by two Brigham Young University graduate students and commissioned by NAIOP and the Society of Industrial and Office Realtors, found a wild variation in costs and time in securing commercial and industrial permits in 2005 among Salt Lake County cities. The study ranked 15 cities and Salt Lake County.

Story continues below
The study ranked office permit costs based on a proposal to build a 50,000-square-foot office building comprising two stories with a 25,000-square-foot floor plate. The building was valued at $4.5 million and proposed for a site consisting of 2.5 acres on a commercial land site.

The five costliest cities in obtaining an office building permit were South Jordan, Draper, Murray, West Jordan and Taylorsville. Cottonwood Heights, at $18,823, was the cheapest city in permit and development fees for a single project.

However, Doug Meldrum, economic development director for South Jordan, questioned the accuracy of the study.

"I found a $204,000 discrepancy from what it says in the report to what our fees actually are for office," Meldrum said. "It really concerned me."

Meldrum was so concerned he wrote a letter to NAIOP, saying that the study's numbers are not comparable. "The impact fees on a younger, growing community would be dramatically different than an older, built-out community," Meldrum said. "That is like comparing apples to oranges."

Even with a $204,000 downward adjustment to South Jordan's permit and development fees, the city would still rank as the most expensive city in the county in obtaining a commercial building permit.

Comments

You can be the first to comment on this story.

Image

View from high-rise on Main Street. Office permitting in Salt Lake City isn't quick or cheap.

previousnext

Latest comments

I alaways make sure to rush out and buy the Christmas concert DVD as soon as...

Priesthood Authority: So many people today fail to recognize the Power of...

I just realized thia is on Verus... Looks like I am going to the HC tomorrow!!

It was a rather difficult experience, not so much for me, as for the...

That's it? That's the whole story? I can't believe that with the tenacity...

they can start in West Valley

No one has yet mentioned the obvious choice, clearly showing the ignorance...

Since they are free tickets, the Conference Center has a formula of what...

I would like to see Boozer back but Memo we Love you but you need to go. We...

I thought the change to Aggie blue was an answer to prayers. Which of you...

Advertisements